Home Extensions & Additions 14 weeks on site

Ground-floor extension, Kingscliff.

Kingscliff. A 45m2 ground-floor extension with matched roofline and new open-plan living area.

Project
062
Completed
Nov 2025
Build time
14 weeks
Footprint
45m2 (9m x 5m)
Dated single-storey brick home in Kingscliff before ground-floor extension Before
Completed ground-floor extension in Kingscliff with matched roofline and new living area After
Ground-floor extension, Kingscliff, Kingscliff. A 45m2 ground-floor extension with matched roofline and new open-plan living area.

The job

What we walked into, and what we did.

The problem

A growing family had outgrown their three-bedroom brick home. The existing living area was small and disconnected from the kitchen. The owners wanted more space but did not want to move, and they needed council approval for the addition.

Our approach

We designed a 45m2 ground-floor extension that matched the existing roofline pitch and brick cladding. The new living area opens directly onto the kitchen and flows through bifold doors to the rear yard. We managed the DA through Tweed Shire Council and engaged the structural engineer at the scoping stage.

The result

The extension was completed on programme and on budget. The council planner commented that the addition reads as original. The owners gained a new living area, a study nook, and a direct connection to the rear garden.

Materials

  • Face brick (matched to existing)
  • Colorbond roofing (matched pitch and colour)
  • Spotted Gum timber flooring

Named in writing

Materials and the honest number.

Cladding Face brick (matched) Colour-matched to existing 1990s brick from the same brickworks
Roofing Colorbond Surfmist
Flooring Spotted Gum 130mm
Glazing Bifold aluminium (4-panel, black)
Fixed-price contract
$185,000 (demo)
All-inclusive: design, engineering, council, construction, handover.
Design and engineering$18,500
Council fees and certification$8,200
Construction$158,300
Price a project like this

14 weeks on site

How the job ran.

  1. Wk 1 to 2

    Slab and footings

    Excavation, formwork, steel, and pour. Engineer inspected before the pour.

  2. Wk 3 to 8

    Frame, roof, and lock-up

    Timber frame, roof sheeting, windows and doors installed. Brickwork commenced.

  3. Wk 9 to 14

    Fit-out and handover

    Internal lining, flooring, painting, bifold installation, landscaping, and defect walk.

On site

A closer look.

“The extension matched the existing roofline so well you cannot tell where the old house ends and the new one starts.”
Sarah M. · Kingscliff
Get started

Start with a measured quote, not a brochure.

Tell us what you want to change about your home. We visit, draw a scope, price every line, and walk you through the council process before you sign anything.